Notice of Non-Payment Deadline Calculator
Enter the day the owner received your invoice. See every prompt payment date under Ontario's Construction Act: when a notice of non-payment is due, when you must be paid, and when subcontractors must be paid.
Your invoice
Not the date printed on it. Use the day it was delivered.
The day the contractor received a Form 1.1, if there was one.
The day the contractor was paid, in full or in part.
Your dates
Enter the day the owner received the invoice to see the dates.
Start the clock with an invoice that qualifies
None of these dates run until the owner has a proper invoice. Make one free, with every field the Act lists. Markup then records when your customer opens it and sends them payment reminders if it goes past due.
Which notice of non-payment form applies
Ontario prescribes five notices of non-payment, Forms 1.1 to 1.5. A notice has to be given on the prescribed form, so use the official one. Download the forms from Ontario Court Forms.
| Form | Given by | Given to | Used when |
|---|---|---|---|
| Form 1.1 | Owner | Contractor | The owner disputes the invoice and will not pay some or all of it. s.6.4(2) |
| Form 1.2 | Contractor | Subcontractor | The contractor cannot pay the subcontractor because the owner has not paid. s.6.5(5) |
| Form 1.3 | Contractor | Subcontractor | The contractor disputes what the subcontractor is owed. s.6.5(6) |
| Form 1.4 | Subcontractor | Its own subcontractor | The subcontractor cannot pay because the contractor has not paid. s.6.6(6) |
| Form 1.5 | Subcontractor | Its own subcontractor | The subcontractor disputes what its own subcontractor is owed. s.6.6(7) |
Common questions
How long does an owner have to give a notice of non-payment in Ontario?
Fourteen days after receiving the proper invoice. The notice must be on Form 1.1 and must state the amount not being paid and all of the reasons. Any amount the notice does not cover is still due within 28 days.
The owner sent me a notice. When do I have to tell my subcontractors?
Within 7 days of receiving the owner’s notice. If the owner simply does not pay and gives no notice, you must give your notice before 35 days have passed since you gave the invoice to the owner. Without a notice, you must pay your subcontractors by that 35-day date.
What if my invoice was missing something?
The owner has 7 days after receiving it to tell you in writing what is deficient and what is needed to fix it. If the owner says nothing in that time, the invoice is deemed to be a proper invoice.
Does this apply outside Ontario?
No. This calculator follows Ontario’s Construction Act only. Alberta, Saskatchewan and Manitoba have their own prompt payment rules with different forms.
Is this legal advice?
No. It counts days from the dates you enter. Your contract and the facts of your job can change what applies, so check with a construction lawyer before you act on a deadline.