Free Lien Deadline
Calculator

The last day you can preserve a construction lien, for every Canadian province, verified against the current statute. Miss this date and the right to preserve a lien is permanently extinguished.

Lien preservation deadline

Lien preservation deadline: September 13, 2026
60 days remaining (60 days from last supply in Ontario).
What starts the clock
Earlier of: publication of CSP, completion / abandonment / termination of contract, or (for subs) last supply
Perfection (next step after preservation)
Plus 90 days to commence court action AND register a Certificate of Action on title (s.36).
Governing statute
Construction Act, SO 2017 c.10 Sch.1, s.31

Lien preservation deadlines across Canada

Every province at a glance. All numbers verified against the current statute as of May 2026.

ProvinceDaysStatute
Ontario60 daysConstruction Act, SO 2017 c.10 Sch.1, s.31
British Columbia45 daysBuilders Lien Act, SBC 1997 c.45, s.20
Alberta60 daysPrompt Payment and Construction Lien Act, RSA 2000 c.P-26.4, s.41
Quebec30 daysCode civil du Québec, art. 2727
Manitoba60 daysThe Builders' Liens Act (amended Bill 38), CCSM c.B91, s.43
Saskatchewan40 daysBuilders' Lien Act, SS 1984-85-86 c.B-7.1, s.49
Nova Scotia60 daysBuilders' Lien Act, RSNS 1989 c.277
New Brunswick60 daysConstruction Remedies Act, SNB 2020 c.29 (replaced the Mechanics' Lien Act, in force April 1, 2022)
Newfoundland & Labrador30 daysMechanics' Lien Act, RSNL 1990 c.M-3
Prince Edward Island60 daysMechanics' Lien Act, RSPEI 1988 c.M-4
Northwest TerritoriesVariesMechanics Lien Act, RSNWT 1988 c.M-7
NunavutVariesMechanics Lien Act (NU consolidation)
YukonVariesBuilders Lien Act, RSY 2002 c.18
General information, not legal advice. This calculator covers the most common preservation rules for each Canadian province. Statutes change; deadlines are strictly enforced; one missed day can permanently void a lien. Many provinces also have separate perfection rules (court action + Certificate of Action) within a longer window. Failing the perfection step also kills the lien. Before relying on any date, confirm with the current statute or a licensed lawyer in your province. Markup is a software platform, not a law firm.
Stop running this calc by hand

Markup tracks lien deadlines for every project automatically.

Every project gets a lien-deadline alert at days 14 and 7 before expiry. Plus Construction Act invoicing, T5018 filing, holdback, and HST/GST/PST per province.

Start free 14-day trial